Expected salable-unit cost assuming all reworked units succeed and the unreworked failures yield the supplied scrap value.

Loading tool…

Description

Estimate salable-unit cost after expected rework and scrap credits under a supplied production scenario.

A startup unit-cost or price comparison needs an explicit denominator and treatment of setup costs, scrap, occupancy and fees. A nominal discount, net unit cost and implied value answer different questions.

Estimate salable-unit cost after expected rework and scrap credits under a supplied production scenario.

When to use this tool

Use Prototype Rework Unit Cost Term when checking a specified unit price, prototype cost or program-price comparison.

How to use the tool and how it works

  1. Enter builtUnits, failedUnits, reworkFraction, reworkCost, scrapValue, initialCost. Use the units and conventions below.
  2. Run the tool. Correct any format, range, or cross-field input error before interpreting the output.
  3. Read reworkUnits, netCost, costPerSalableUnit. Use the output convention below.

Require whole builtUnits >= 1 and failedUnits between zero and builtUnits, reworkFraction in [0,1] and nonnegative reworkCost, scrapValue and initialCost. reworkUnits = failedUnits*reworkFraction; netCost = initialCost+reworkUnits*reworkCost-(failedUnits-reworkUnits)*scrapValue. Divide netCost by builtUnits-failedUnits+reworkUnits, which must be positive, for costPerSalableUnit.1

Input fieldMeaning and unitsAccepted input
builtUnitsBuilt UnitsRequired. Safe integer; minimum 1.
failedUnitsFailed UnitsRequired. Safe integer; minimum 0.
reworkFractionFraction of failed units assumed successfully reworked; may produce fractional modeled units.Required. Finite number; minimum 0; maximum 1.
reworkCostRework CostRequired. Finite number; minimum 0.
scrapValueScrap ValueRequired. Finite number; minimum 0.
initialCostInitial CostRequired. Finite number; minimum 0.
Output fieldInterpretationReturned shape
reworkUnitsRework UnitsRequired. Finite number.
netCostNet CostRequired. Finite number.
costPerSalableUnitCost Per Salable UnitRequired. Finite number.
json
{
  "input": {
    "builtUnits": 100,
    "failedUnits": 20,
    "reworkFraction": 0.5,
    "reworkCost": 10,
    "scrapValue": 2,
    "initialCost": 1000
  },
  "output": {
    "reworkUnits": 10,
    "netCost": 1080,
    "costPerSalableUnit": 12
  }
}

Limitations and assumptions

  • Rework fractions model expected units, so counts can be fractional. Scrap credits may make net cost negative; rework success, demand and complete production costs are not inferred.
  • Inputs must satisfy both the field types and the cross-field conditions above. Invalid input causes an error; a successful false flag or documented placeholder is a different result.
  • Numeric calculations use binary floating point unless exact decimal-integer arithmetic is explicitly stated. No hidden measurement tolerance or decimal rounding is added; nonfinite or out-of-contract results are rejected. Numeric signed-zero results are exported as zero.

Alternative or Complementary methods

Use a complete cost and revenue model when fixed costs, variable yields, market comparability or timing change the interpretation.

References

  1. Calculation and input contract: entrepreneurship-studies/prototype-rework-unit-cost-term — tool.io

Similar or alternative tools