Description
chargedEnergy = energy/(1-lossFraction) when grossUpLosses is true, otherwise energy; costAdder = chargedEnergy*suppliedAdderPerEnergy.
Energy price comparisons require consistent delivered or input energy units, efficiency, calorific basis and reporting period. Dividing by efficiency increases the input needed for a delivered unit; nominal price differences alone need not represent a saving.
chargedEnergy = energy/(1-lossFraction) when grossUpLosses is true, otherwise energy; costAdder = chargedEnergy*suppliedAdderPerEnergy.
When to use this tool
Use Dispatch Cost Adder Component when checking one supplied energy-price normalization or cost contribution.
How to use the tool and how it works
- Enter energy, suppliedAdderPerEnergy, suppliedLossFraction, grossUpLosses. Use the units and conventions below.
- Run the tool. Correct any format, range, or cross-field input error before interpreting the output.
- Read costAdder, chargedEnergy. Use the output convention below.
Require nonnegative energy and suppliedLossFraction in [0,1). chargedEnergy = energy/(1-lossFraction) when grossUpLosses is true, otherwise energy; costAdder = chargedEnergy*suppliedAdderPerEnergy.1
| Input field | Meaning and units | Accepted input |
|---|---|---|
| energy | Energy | Required. Finite number; minimum 0. |
| suppliedAdderPerEnergy | Supplied Adder Per Energy | Required. Finite number. |
| suppliedLossFraction | Supplied Loss Fraction | Required. Finite number; minimum 0; strictly below 1. |
| grossUpLosses | Gross Up Losses | Required. Boolean. |
| Output field | Interpretation | Returned shape |
|---|---|---|
| costAdder | Cost Adder | Required. Finite number. |
| chargedEnergy | Charged Energy | Required. Finite number. |
{
"input": {
"energy": 80,
"suppliedAdderPerEnergy": 2,
"suppliedLossFraction": 0.2,
"grossUpLosses": true
},
"output": {
"costAdder": 200,
"chargedEnergy": 100
}
} Limitations and assumptions
- Losses are a fraction of gross energy. The adder may be signed and is supplied rather than derived from network losses, dispatch costs or a tariff.
- Inputs must satisfy both the field types and the cross-field conditions above. Invalid input causes an error; a successful false flag or documented placeholder is a different result.
- Numeric calculations use binary floating point unless exact decimal-integer arithmetic is explicitly stated. No hidden measurement tolerance or decimal rounding is added; nonfinite or out-of-contract results are rejected. Numeric signed-zero results are exported as zero.
Alternative or Complementary methods
Use the full tariff, operating profile and cost boundary when assessing real bills, investments or load-shifting decisions.
References
Similar or alternative tools
- Storage Degradation Cost One Cycle Term
costPerCycle = (replacementCost-residualValue)/lifetimeCycles; costPerMwh divides that by dischargedMwhPerCycle.
- Storage Roundtrip Cost Term
outputUnitCost = inputEnergyPrice/roundtripEfficiency+outputOtherCost.