Task Dependency Finish Start Lag Tool

Calculate task dependency finish start lag from explicit caller-supplied inputs.

Loading tool…

Description

Add lag to predecessorFinish for dependencyStart, then take the later of that value and successorEarliest for scheduledStart.

Schedule differences use a common time coordinate and may preserve negative slack or lead times. A scalar lag or float term does not recalculate a full dependency network.

Add lag to predecessorFinish for dependencyStart, then take the later of that value and successorEarliest for scheduledStart.

When to use this tool

Use Task Dependency Finish Start Lag when you need one explicit scheduling or delay-budget component.

How to use the tool and how it works

  1. Enter predecessorFinish, lag, successorEarliest. Use the units and conventions below.
  2. Run the tool. Correct any format, range, or cross-field input error before interpreting the output.
  3. Read dependencyStart, scheduledStart. Use the output convention below.

Add lag to predecessorFinish for dependencyStart, then take the later of that value and successorEarliest for scheduledStart.1

Input fieldMeaning and unitsAccepted input
predecessorFinishPredecessor FinishRequired. Finite number.
lagLagRequired. Finite number.
successorEarliestSuccessor EarliestRequired. Finite number.
Output fieldInterpretationReturned shape
dependencyStartDependency StartRequired. Finite number.
scheduledStartScheduled StartRequired. Finite number.
json
{
  "input": {
    "predecessorFinish": 10,
    "lag": 2,
    "successorEarliest": 11
  },
  "output": {
    "dependencyStart": 12,
    "scheduledStart": 12
  }
}

Limitations and assumptions

  • Negative lag is allowed; all coordinates must share a unit and calendar, and other dependencies are not considered.
  • Inputs must satisfy both the field types and the cross-field conditions above. Invalid input causes an error; a successful false flag or documented placeholder is a different result.
  • Numeric calculations use binary floating point unless exact decimal-integer arithmetic is explicitly stated. No hidden measurement tolerance or decimal rounding is added; nonfinite or out-of-contract results are rejected. Numeric signed-zero results are exported as zero.

Alternative or Complementary methods

Use a complete dependency plan and working calendar to assess critical paths, resource constraints, and completion forecasts.