Description
Calculate a progress-claim balance using supplied material and prior-claim values.
Construction records combine revisions, dates, dimensions, rental periods, claims and financial balances. Revision numbers need not be consecutive, calendar offsets differ from business days, and recoverable length can depend on a strict cutoff. A supplied approval or readiness label is a record assertion rather than an engineering inspection or contractual determination.
Calculate a progress-claim balance using supplied material and prior-claim values.
When to use this tool
Use Progress Claim Stored Material Adjustment when you already have workValue, eligibleStoredMaterialValue, previouslyClaimedValue and need to calculate a progress-claim balance using supplied material and prior-claim values.
How to use the tool and how it works
- Enter workValue, eligibleStoredMaterialValue, previouslyClaimedValue. Use the units and conventions below.
- Run the tool. Correct any format, range, or cross-field input error before interpreting the output.
- Read currentClaimValue. Use the output convention below.
Require all three amounts>=0; return work+eligibleStoredMaterial-previouslyClaimed.1
| Input field | Meaning and units | Accepted input |
|---|---|---|
| workValue | Work Value | Required. Finite number; minimum 0. |
| eligibleStoredMaterialValue | Eligible Stored Material Value | Required. Finite number; minimum 0. |
| previouslyClaimedValue | Previously Claimed Value | Required. Finite number; minimum 0. |
| Output field | Interpretation | Returned shape |
|---|---|---|
| currentClaimValue | workValue+eligibleStoredMaterialValue-previouslyClaimedValue; negative bookkeeping values are retained. | Required. Finite number. |
{
"input": {
"workValue": 1000,
"eligibleStoredMaterialValue": 200,
"previouslyClaimedValue": 700
},
"output": {
"currentClaimValue": 500
}
} Limitations and assumptions
- Negative claims are retained. Eligibility, valuation, disjoint amounts, contract terms, approval and actual payment are not verified.
- Inputs must satisfy both the field types and the cross-field conditions above. Invalid input causes an error; a successful false flag or documented placeholder is a different result.
- Numeric calculations use binary floating point unless exact decimal-integer arithmetic is explicitly stated. No hidden measurement tolerance or decimal rounding is added; nonfinite or out-of-contract results are rejected. Numeric signed-zero results are exported as zero.
Alternative or Complementary methods
Check controlled drawings, site measurements, schedules, approvals and the complete contract. Use the appropriate engineering assessment and actual billing or claim terms when a local scalar calculation or date comparison cannot establish suitability or entitlement.
References
Similar or alternative tools
- Retention Payment Release Balance
Update a supplied retention balance after additions and release.
- Construction Pay Item Quantity Variance
Compare supplied installed, contracted and paid quantities.